Identification and Allocation of Risks Associated with PPP Water Projects in China/Su Kinijos Vandens Projektais, Pagristais Viesojo Ir Privaciojo Sektoriu Partneryste, Susijusiu Rizikos Rusiu Nustatymas Ir Paskirstymas (Report) Identification and Allocation of Risks Associated with PPP Water Projects in China/Su Kinijos Vandens Projektais, Pagristais Viesojo Ir Privaciojo Sektoriu Partneryste, Susijusiu Rizikos Rusiu Nustatymas Ir Paskirstymas (Report)

Identification and Allocation of Risks Associated with PPP Water Projects in China/Su Kinijos Vandens Projektais, Pagristais Viesojo Ir Privaciojo Sektoriu Partneryste, Susijusiu Rizikos Rusiu Nustatymas Ir Paskirstymas (Report‪)‬

International Journal of Strategic Property Management 2011, Sept, 15, 3

    • $5.99
    • $5.99

Publisher Description

1. INTRODUCTION The construction engineering is beset with a high degree of risk due to its complexity, particularly in coordinating a wide range of disparate and interrelated skills and activities under the constraint of time and resources (Deviprasadh, 2007; Tieva and Junnonen, 2009; Leung and Hui, 2005). For PPP projects, such complexity is further compounded by its additional external uncertainties and the wide extension of the disciplines, public agencies and various stakeholders involved (Thomal et al., 2006). PPP stakeholders are exposed to high risks as projects typically involve high capital outlays, long lead times, and long-lived assets with little value in alternative use (Zayed and Chang, 2002). With PPP projects becoming increasingly complex, industrial practitioners have to rethink their measures to risk management within their projects and organizations (Carr and Tah, 2001). It is reported that a majority of PPP projects in China encountered cost overrun, schedule delay, or failed to deliver service as defined in the concession agreement (Zeng et al., 2008). The main causes for such predicaments include (1) a lack of effective risk evaluation procedure; (2) underestimation of the time and resource limit; (3) insufficient consideration of changes in project implementation; and (4) undervaluing the changes in exchange rates. The need for establishing an effective risk management for PPP projects is becoming more urgent (Choi et al., 2004).

GENRE
Business & Personal Finance
RELEASED
2011
1 September
LANGUAGE
EN
English
LENGTH
40
Pages
PUBLISHER
Vilnius Gediminas Technical University
SELLER
The Gale Group, Inc., a Delaware corporation and an affiliate of Cengage Learning, Inc.
SIZE
364.6
KB

More Books Like This

Long-Term Investments Long-Term Investments
2020
Risk Management Risk Management
2021
Project Finance Project Finance
2005
Project Finance Project Finance
2020
Quantitative Financial Risk Management Quantitative Financial Risk Management
2011
The Principles of Project Finance The Principles of Project Finance
2016

More Books by International Journal of Strategic Property Management

Risk Management in Projects: Peculiarities of Lithuanian Construction Companies/Rizikos Valdymas Projektuose: Lietuvos Statybos Imoniu Savitumai (Report) Risk Management in Projects: Peculiarities of Lithuanian Construction Companies/Rizikos Valdymas Projektuose: Lietuvos Statybos Imoniu Savitumai (Report)
2011
An Empirical Investigation of Procurement Trends and Partnership Management in FM Services--a Finnish Survey (Facilities Management) An Empirical Investigation of Procurement Trends and Partnership Management in FM Services--a Finnish Survey (Facilities Management)
2006
Legislation for Effective Post-Disaster Reconstruction/ Efektyvaus Aplinkos Atstatymo Po Stichiniu Nelaimiu Istatymai (Report) Legislation for Effective Post-Disaster Reconstruction/ Efektyvaus Aplinkos Atstatymo Po Stichiniu Nelaimiu Istatymai (Report)
2009
Property Market Nature and the Choice of Property Portfolio Diversification Strategies: The Nigeria Experience/Nuosavybes Rinkos Prigimtis Ir Nuosavybes Portfelio Diversifikacijos Strategijos Pasirinkimas: Nigerijos Patirtis (Report) Property Market Nature and the Choice of Property Portfolio Diversification Strategies: The Nigeria Experience/Nuosavybes Rinkos Prigimtis Ir Nuosavybes Portfelio Diversifikacijos Strategijos Pasirinkimas: Nigerijos Patirtis (Report)
2008
Developing Capacities for Disaster Risk Reduction in the Built Environment: Capacity Analysis in Sri Lanka/ Gebejimo Mazinti Nelaimiu Keliama Rizika Uzstatytoje Aplinkoje Ugdymas: Gebejimu Analize Sri Lankoje (Report) Developing Capacities for Disaster Risk Reduction in the Built Environment: Capacity Analysis in Sri Lanka/ Gebejimo Mazinti Nelaimiu Keliama Rizika Uzstatytoje Aplinkoje Ugdymas: Gebejimu Analize Sri Lankoje (Report)
2010
Capacity Building Lessons from a Decade of Transitional Settlement and Shelter/ Per Desimt Metu Ismoktos Potencialo Didinimo Pamokos Aprupinant Laikinosiomis Gyvenamosiomis Vietomis Ir Suteikiant Prieglaudal (Santrauka) Capacity Building Lessons from a Decade of Transitional Settlement and Shelter/ Per Desimt Metu Ismoktos Potencialo Didinimo Pamokos Aprupinant Laikinosiomis Gyvenamosiomis Vietomis Ir Suteikiant Prieglaudal (Santrauka)
2009