W. J. Haney v. L. R. Foy Construction Co. W. J. Haney v. L. R. Foy Construction Co.

W. J. Haney v. L. R. Foy Construction Co‪.‬

NE.55 , 184 N.W.2d 628, 528 (1971)(186 Neb)

    • € 0,99
    • € 0,99

Publisher Description

The plaintiff, W. J. Haney, brought this action to recover the balance due on a construction subcontract in which the defendant,
L. R. Foy Construction Co., Inc., was the principal contractor. The jury returned a verdict for the plaintiff and the defendant
has appealed. The plaintiff contracted to perform the plastering and lathing work on the Golden Towers Housing Project building at Grand
Island, Nebraska. The parties stipulated that the total amount of the plaintiff's contract was $40,046 and that the defendant
had paid $33,572.85 to the plaintiff and to the plaintiff's suppliers for the benefit of the plaintiff. The verdict was for
the difference between these amounts, $6,473.15.

GENRE
Professional & Technical
RELEASED
1971
12 March
LANGUAGE
EN
English
LENGTH
2
Pages
PUBLISHER
LawApp Publishers
SIZE
58.8
KB

More Books by Supreme Court of Nebraska

Rosemary Schieffer v. Catholic Archdiocese Rosemary Schieffer v. Catholic Archdiocese
1993
City of Gordon v. Montana Feeders City of Gordon v. Montana Feeders
2007
State Nebraska v. Arthur Lyle State Nebraska v. Arthur Lyle
1994
Ervin Melcher v. Bank Madison Ervin Melcher v. Bank Madison
1995
Bridgette A. Anderson and Candy S. Bridgette A. Anderson and Candy S.
1995
Heath Consultants v. Precision Instruments Heath Consultants v. Precision Instruments
1995