The Final Order, 101 Pub. Util. Rep. (PUR) 4th at 131-40, summarizes the factual background and discusses the procedural history of this case. For the purposes of this appeal, it is sufficient to understand that PNM over the last several decades had invested in excess generating capacity, including portions of PVNGS. The Commission initially had addressed this problem through inventory ratemaking, see New Mexico Indus. Energy Consumers v. New Mexico Pub. Serv. Comm'n, 104 N.M. 565, 725 P.2d 244 (1986), which allowed PNM to accrue carrying costs for its investment in capacity not yet needed by energy consumers. That stop-gap solution proved to be ineffective, leading the Commission to consider the problem anew.